Little Rock — Expert Advice
Rail Transit Online, September 2000
A two-day peer review of the proposed
1.9-mile River Rail streetcar system connecting downtown Little Rock with North
Little Rock has determined that the trolleys will require an emergency braking
system for added safety on the Main Street Bridge. Examining the plan were
Frank Tobey, Resident Manager of the Memphis Area Transit Authority; Frank
Menair, Manager of Commuter Rail Construction and Maintenance for Trinity
Railway Express; the legendary Elmer von Dullen, trolley maven and
Superintendent of Maintenance for the Regional Transit Authority in New Orleans;
and Cheryle Tyson, an engineer from the Federal Transit Administration. Both
Tobey and von Dullen have extensive expertise with historic streetcars, and it
was Tobey who mentioned the brakes after expressing concern over the steep eight
percent curving grade at the north end of the bridge where it enters North
Little Rock. The group also suggested that CATA make certain the three cars
recently ordered from Gomaco, which will have four 25-hp. motors, will be
sufficiently powerful to carry a loaded car up and around the curve. Planners
said they are already working on the brake issue and Gomaco has assured transit
officials that the trolleys will perform to specification. “It's been an
extremely useful two days,” Keith Jones, Executive Director of the Central
Arkansas Transit Authority, told the Arkansas Democrat-Gazette
newspaper. “We didn't hear too much the design team hadn’t thought about at
some level. Safety was sort of the overwhelming concern and message we got from
the team.” The cars (there’s an option for a fourth) will be similar to those
ordered by Tampa for the Ybor City Line. However, according to John Kallin and
Travis Ellis at Gomaco, the Little Rock units, with a length of 45.5 ft., will
be two windows shorter than those being built for Tampa. Also, they will not
have bulkheads between the car platform and body and will have two wheelchair
lifts (at each end in the forward door) instead of one, the latter a primary
reason that the Little Rock cars will cost $750,000 each compared with $609,000
per car for Tampa. Either price is a bargain, probably owing to the use of
trucks and controls from scrapped Peter Witts purchased from the Milan, Italy,
transit system. Plans call for completing eight cars for Tampa, then three for
Little Rock, then the remaining four for Tampa. The first vehicle should arrive
in Little Rock in the fall of 2001. The project is now estimated to cost
between $12.3 million and $13.5 million. Construction bids probably won’t be
advertised until at least December, and completion is expected in late 2001 or
early 2002. CATA officials expect Congress to act later this month on a $5.7
million appropriation for the project.
|
|